Downtime
Last modified by Андрей Калиновский on 2023/04/26 11:00
The report displays information about downtime of objects that last more than 60 minutes. The report data is broken down by day (this is called a shift in report terms). Within a day, a list of stops is formed, which can be both inside geo objects and outside.
Report structure:
- Object name;
- Shift - a period equal to a day, during which equipment downtime was detected;
- Simple - the period of parking of equipment;
- Duration of downtime and location - one cell of the table indicates the duration of the parking of equipment and its location at the time of parking;
- Idle duration XX and location - indicates the duration of idling during parking, as well as the location of the object;
- Lane number - the number of the haul is increased after the geo object stops.